Residents of ZATO Zheleznogorsk in the Krasnoyarsk Territory risk being left without heat and electricity. On May 31, the main source of heat supply for their city, the ADE-2 nuclear reactor, will be shut down. The new thermal power plant, which was promised to be put into operation by the time the reactor was shut down, was never built. And it won't be built soon. Local deputy Sergei Afonin decided to draw the attention of the first persons of the state to the problem. He started a blog on LiveJournal and commented on this topic on President Dmitry Medvedev's blog. A few days later, Afonin was contacted by "people from Moscow" who asked him to "withdraw the comment." The deputy refused.
The nuclear reactor ADE-2 was launched at the mining and chemical plant for the production of weapons-grade plutonium in Zheleznogorsk 45 years ago - to the already operating reactors AD and ADE, but unlike them, it was used to generate electricity, hot water and heating for the needs of the city. Shutting down the reactors began in the 1990s, under an agreement between the United States and Russia to stop plutonium production. AD and ADE stopped working in 1992, the fate of ADE-2 was finally decided in 1997 - it was to be closed before 2010. In return, Zheleznogorsk was to receive a new thermal power plant, completely replacing the old reactor in terms of capacity.
The construction of the CHPP began in 2006 by Rosatom. It was assumed that the facility would consist of three start-up complexes (one of which, namely the third, would be responsible for generating electricity), and it would be commissioned in 2008. True, in September 2008 the commissioning of the CHPP was postponed for a year, with the expectation that by the winter season of 2009-2010 the facility would still work. It was assumed that 1 launch complex will work on May 25, the second - on September 25, 2009.
But in March, specialists from OAO Yenisei TGC (TGC-13) analyzed the readiness of the Zheleznogorsk CHPP (although now it is called Krasnoyarsk CHPP-4, we will stick to the old name in this article, - note TAIGA.info). The conclusions are disappointing. The readiness of the Zheleznogorsk CHPP under construction raises doubts about the possibility of putting into operation 1 and 2 start-up complexes on schedule, - Vladimir Bogomazov, General Director of TGC-13, wrote to the Minister of Energy and Industry of the Territory, Mr. no earlier than June 2010.
And if the construction of a thermal power plant can be postponed, then shutting down the reactor is absolutely impossible. And this stop will be made on May 31. Against this background, it is very informative to read documents dated 2008. The documents say that at a joint meeting with the head of Rosatom Sergey Kiriyenko and the governor of the Krasnoyarsk Territory Alexander Khloponin, dedicated to this problem, the participants decided to “confirm that the ADE-2 reactor will not be stopped until the 1 and 2 start-up complex of the ZhTES is put into operation” .
“I have four children, the youngest - twins - are not yet two years old. Therefore, as I imagined what we would do with them without hot water and how to live in winter, I realized that something urgently needed to be done. I decided to start a blog on LiveJournal and write to President Medvedev , saying, so and so, help the city, a hundred thousand people are at risk of leaving for the harsh Siberian winter without enough heat and hot water, ”Sergey, deputy of the Council of Deputies of ZATO Zheleznogorsk, told TAIGA.info Afonin.
A few days later, the MP got a call. “The number was definitely Moscow, the interlocutor introduced himself, but I did not remember the name,” says Afonin. - They asked me to withdraw the comment on the president's blog, but I said that, firstly, I did not have the technical ability, but even if I had, I still would not withdraw anything. You know, getting a hat from the authorities is not as scary as being left without heat in winter with small children.
According to the MP, after the comment was published on the president's blog, something stirred at the local level. “I don't think it was the president who reacted so quickly, rather, our officials are working ahead of the curve,” says Afonin.
Afonin's colleagues in the deputy corps reacted ambiguously to his initiative: someone supported, while someone, on the contrary, expressed the idea, they say, why write to the president with such problems. However, the deputy himself does not intend to abandon his blog on the Internet - he discovered there "a conglomerate of thinking people." And yes, it will still come in handy.
As for the fate of the ZhCHP, which, thanks to the initiative of Afonin and the recent conference of Siberian bloggers "Novoblogika" (where, in fact, this story was told), has now drawn the attention of a good half of the "conglomerate of thinking people", then she, this fate, still incomprehensible. The head of Zheleznogorsk, Gennady Bakhovtsev, issued a statement on April 27, describing the situation as "extremely serious." “If Rosatom, as its representatives now say, shuts down the ADE-2 reactor before the station's two start-up complexes are ready, Zheleznogorsk's uninterrupted heat supply will be in jeopardy,” he said. - We hoped to the last that such a development of events would not happen, since the head of the state corporation - Sergey Kiriyenko - and his people promised both us and the governor of the Krasnoyarsk Territory that the deadlines for commissioning the CHPP would not be disrupted, and in any case, the reactor would continue to work until its final intro for exploitation. This is not only oral, but also documentary evidence. Unfortunately, the latest statements by representatives of Rosatom about shutting down the reactor in May this year 2009 lead to the conclusion that this promise will remain unfulfilled. I would like to note that local self-government bodies of Zheleznogorsk completed their part of the work on time. With great difficulties, cutting to the quick, but we nevertheless found funds and built the DU-1000 pipeline connecting the heating networks of the territory and the CHPP site. However, there is nothing to connect it to today. The hasty shutdown of the reactor cannot but cause concern for three reasons. Firstly, the territory is left with only one oil-fired boiler as a heat source, which means that in the event of an emergency, there will be no reserve. Secondly, a serious issue arises with the supply of hot water to the city (now the heating system is replenished from the reactor). Thirdly, fuel oil heat is a 2.5-3 times increase in tariffs. The source to cover such expenses has not yet been determined.”
Rosatom did not take long to wait: on April 29, Sergei Kiriyenko signed an order "prescribing the shutdown of the ADE-2 reactor, ensuring, if necessary, its launch for heating and hot water supply to Zheleznogorsk." The operation of the reactor for 2009-2010 will be ensured in standby mode. “Work on the preparation of the order,” the report says, “began long before the announcement of the intention to shut down the reactor after the 2008-2009 heating season, so possible speculation by individual public figures that it was their position that influenced the decision of Rosatom should be regarded as an attempt build political capital on the responsible position and result of the work of other people and organizations”.