Today, the head of Abakan Alexei Lemin held the next headquarters for the implementation in the republican capital of the national project “Safe and high -quality roads”.
For many objects, for various reasons, there are difficulties in compliance with the terms of contracts, withstanding the schedule-graph of the work, providing facilities with sufficient reserves of building materials, including ASS, bitumen, asphalt. Some objects are not enough working hands and equipment, on some difficulties with the conduct of, for example, earthwork. For all delays in the performance of work, according to contracts, the contractors will present penalties, including on Pushkin Street, according to the Abakan administration.
Ekaterina Makarova, chief specialist of the Department of Urban Planning, Architecture and Land Management of the Abakan administration:
- Work on Rosa Luxemburg Street has been completed. The length of the section of the Rosa Luxembourg road under the overhaul of the asphalt concrete coating is about 600 meters, in the repair work zone there are three rainfall and water -absorbing wells. The roadway was repaired by the contracting organization of DSU-1 LLC within the borders of the streets of Havan-the fallen Kommunarov. On the Street of the Palim Kommunarov, more than half of the planned work was completed, the contract was valid, by the beginning of October we are waiting for the full completion of the work from contractors. The reconstruction of the Street of the Pali Kommunarov is coming from Okovskaya Street to Nagornaya Street, the area of the new road surface is almost 32 thousand square meters. According to Nekrasov, work continues. Now laying the upper layer of asphalt concrete coating in parking lots is performed. Next week, the contractor will begin milling the roadway within the borders of Shchetinkin - Kirov. The laying of the cable line under the lighting of lighting continues. Litvinova Street is a little more complicated. The full number of cable lines under the roadway prevents the full performance of work, the contractor is forced to almost manually remove the soil to replace the base, and there is a fairly large depth. But from next week, the contractor plans to begin asphalting of the carriageway from the side of Rossskaya Street. On Central Street by the end of next week, the contractor plans to start laying the upper layer of asphalt concrete coating.