| Rostekhnadzor finally approved the project to build an oil pipeline to the Pacific Ocean It seems that nothing is stopping Transneft from starting construction of an oil pipeline from Eastern Siberia to the Pacific Ocean. The head of the working group of the Rostekhnadzor commission, Gennady Chegasov, told Vremya Novostey yesterday that on February 28, the majority of experts supported the pipeline construction option proposed by Transneft. True, this happened only after the composition of the commission was expanded by a third - a month ago, environmental experts refused to approve the necessary documents. Mr. Chegasov himself considers the decision “illegal,” and environmental organizations agree with him, in particular the Russian representatives of Greenpeace and the Wildlife Fund (WWF) - they are confident that laying the pipe along the approved route could cause irreparable harm to Baikal. However, Greenpeace does not intend to give up. Recently, this organization contacted the largest international banks - Barclays Plc, ABN Amro, Fortis Bank, Citigroup and ING Bank - with an official letter warning about possible legal risks when financing the project. Greenpeace hopes that this will interfere with construction, which is estimated at $6.5 billion, since Transneft does not have its own funds and intends to carry it out with borrowed money.
The pipeline from Eastern Siberia is planned to be built in two stages. The starting point will be Taishet (Irkutsk region), from which the pipe will be laid to Skovorodino (Amur region). From there, the raw materials will be transported by rail to the Pacific coast, where an export terminal is expected to be built by the end of the pipeline. The pipeline's capacity at the first stage will be 30 million tons of oil per year. Then, according to the Energy Strategy until 2020, a pipeline will connect Skovorodino and the terminal. At the same time, the power of the pipe will be increased. True, for now these are nothing more than plans.
Last year, approval of the project’s feasibility study was received from all interested departments, with the exception of Rostekhnadzor, which was supposed to sign the conclusion on January 25. However, this did not happen. “It is felt that the leadership of the department does not want to agree with the conclusions of the experts and approve the conclusions of the commission,” Mr. Chegasov said then. Even then, he did not rule out that a new expert group would be created, “which would make the ‘necessary’ decision.” After all, Vladimir Putin quite often repeated last fall that environmentalists are unreasonably slowing down large government projects, and this, according to the president, is unacceptable.
The essence of the disagreement is that part of the pipeline will be laid 800 meters from Lake Baikal, and environmentalists consider this dangerous. They are confident that the measures to protect against a possible spill of raw materials provided by Transneft are insufficient, because the pipe is located in a seismically active zone with an intensity, according to Mr. Chegasov, of ten or more. Transneft says that the project provides for unprecedented safety measures, including double lining of the pipe. At the same time, the company reminds that the pipeline will pass outside the water protection zone defined by law.
At the meeting of the first commission, 46 out of 52 experts signed a negative opinion on the project. As Mr. Chegasov explained yesterday, to approve the document it is necessary to collect two-thirds of the votes. However, the head of Rostekhnadzor, Konstantin Pulikovsky, did not agree with the commission’s conclusion. It was decided to expand its composition to 89 people and extend its work until March. And on February 28, the majority of experts supported the project. According to information from Russian Greenpeace representative Roman Vazhenov, only 23 people were against it. “There are no environmentalists among the experts who signed the positive decision; they are all mechanical engineers. There was not a single seismic specialist,” complains Mr. Chegasov, in turn.
The conclusion of Rostekhnadzor must be signed before March 3. Mr. Pulikovsky’s department did not say yesterday whether this would be done. Denis REBROV |
|