The major renovation of Tomsk boarding school No. 33 for visually impaired and blind children should have been completed a year ago. But, as Rush Hour reports , the deadline for commissioning the facility has been delayed.
The construction company that was renovating the building received money for part of the work performed and liquidated itself. And the director of the boarding school was convicted of extortion. According to investigators, he extorted 250 thousand rubles from the contractor for signing a work completion certificate. Despite the fact that the work was performed poorly.
The renovation of the building was carried out by the Novosibirsk company Success LLC . She got the object through a competition in which “ Success ” reduced the price from 40 million rubles to 39. Having received more than 23 million rubles, the construction company closed, leaving the facility in a state of repair. As the new director of boarding school No. 33, Igor Fillipov, explained, by law they could file claims against the contractor for poor-quality repairs, but since the company liquidated itself, there is no one to file claims against .
After this, a new competition was announced to complete the renovation. Another 16 million rubles were allocated for these purposes. According to the contract, the contractor must complete the repairs by the end of the year, but another problem arose - the roof was leaking.
" In an amicable way, the contractor had to come and see what he was going to do here. There were 4 applicants in the competition , some of them came, looked, and then decided whether they would be in the competition . But this contractor did not come, did not look “I won, and then I came . It turned out that everything was not as I wanted, ” explained Igor Fillipov.
In turn, rumors have already spread among the parents of boarding school students that the boarding school building may be taken away from their children.
“ There was a meeting scheduled at RANO or the Department of Education, there was a rumor that the school could be taken away from such children altogether . The building itself could be taken away, ” Tomsk resident Yuri Yakimov, whose son studied at boarding school No. 33, told the “ Rush Hour ” reporters.
During the renovation, the boarding school students were distributed to other institutions, not all of which are suitable for teaching blind and visually impaired children. The next deadline for completing the school's overhaul is mid- December this year.