On January 29, a competition for the construction of a new building for the St. Petersburg City Court should finally take place. However, it is far from certain that it will take place or that its results will be recognized as valid. Observers do not rule out that the customer, the local judicial department, is in a hurry and is “pushing through” the previously known winner in this tender.
They want to recover 3.5 billion rubles from the City Court
The St. Petersburg City Court has long been in a deplorable state: it is scattered across three sites, and one of the buildings where judges sit is in disrepair. At the same time, the behind-the-scenes struggle for the right to develop almost 3.5 billion rubles (this is the current project budget) has led to the fact that for more than a year the decision to construct a new building has not moved forward in any way, despite the fact that two and a half hectares in the Moscow region.
According to plans, construction was supposed to begin in January 2007. However, the conflict between the customer - the Office of the Judicial Department at the Supreme Court of the Russian Federation - and Lenenergo delayed the preparation of the project, and it was approved by the State Expertise only last fall. But then the customer and the designer, Lenmontazh LLC, suddenly stopped understanding each other.
It got to the point that the issue of delaying construction was considered by the permanent commission of the St. Petersburg Legislative Assembly on issues of law and order and legality under the leadership of Arkady Kramarev. Based on its results, a letter was written to prosecutor Sergei Zaitsev, which, according to competent sources, greatly displeased the head of the SD Directorate, Valery Selyukov. Perhaps it was Selyukov’s resentment towards Lenmontazh that was the reason that on December 11, the Office of the Judicial Department announced a competition for “the provision of services for the development of working documentation and construction” of the St. Petersburg City Court building. In response to this, the designers - Lenmontazh - filed a complaint about the illegality of holding the competition with the FAS.
The complaint contains two inconvenient points for the customer. Firstly, the development of working documentation has already been partially completed by Lenmontazh LLC and accepted by the Office of the Judicial Department, as evidenced by the work acceptance certificates. This means that a competition is being announced for work that has been partially completed and paid for, and the SD management is ready to pay money a second time for the same work.
Secondly, a construction competition cannot be held until all project documentation is ready. By law, working documentation is included in the project, but it has been partially completed.
FAS agreed that there were some procedural violations in the tender and invited the Board of Directors to correct them. As a result, the opening of the envelopes was postponed from January 17 to January 29. However, the FAS considered the main issue not to be within its competence and referred the complaints to Rosfinmonitoring and the Prosecutor General’s Office. Lenmontazh, in turn, sent a second letter to the antimonopoly authorities and contacted the City Prosecutor's Office.
Experts are most alarmed by the haste with which the competition was announced in December and then postponed. The fact is that from January 1, 2008, construction orders must be placed only through open auctions. Then the rush can be explained by the fact that the tender had to be announced before the new year, which is what happened. Market observers do not exclude in this case the operation of a scheme in which the interests of a specific contractor company, the potential winner of the competition, are pursued (remember, almost 3.5 billion rubles are at stake). We decided not to voice the versions expressed about companies “interested” in a positive outcome of the competition for them. If only because the event itself on January 29 may easily not take place, since the situation is now being monitored by several federal departments and the City Prosecutor's Office. At the time of publication, we were unable to obtain comments from the Office of the Judicial Department.
Vasily DENISENKO