The processing plant for solid household waste has been replacing a reclaimed Gornostaevsky landfill in Vladivostok for two years. Under the cut, a photo report on how the end point of all garbage flows of the city copes with its tasks.
The complex for sorting and processing the solid waste was built and launched two years ago in the upper reaches of the Nameless stream, not far from the Gornostaevsky landfill closed to the reclamation in preparation for the APEC. Valmirno Khumirnostai after reclamation.
1.

Photo report from February 16, 2010, when this landfill still functioned, you can see here
2.

Since March 2012, the new factory has earned full capacity.
3.

At the main entrance to the complex, a warehouse of recyclables is organized
4.

Weight station
5.

Special vehicles unload garbage in a cold workshop (waste acceptance workshop)
6.

The area of the new landfill is 58.4 hectares. The company is able to process about 300 thousand tons of solid waste per year. According to the production manager Dmitry Kurilov, this is more than enough for Vladivostok. Now the first range of the training ground is open, designed for 7 years.
7.

“When the card is closed, we will carry out the reclamation, as with the“ Gornostaevskaya ”landfill,” says Dmitry Kurilov. “The next card will be open. To date, 5 is planned.”
8.

From the cold workshop, waste comes to the ribbons of sorting. Now there are two semi -automatic technological lines, designed for processing 20 tons of garbage per hour
9.

The sort of waste on recyclables and useless garbage occurs manually.
10.

Personnel in masks and gloves separates plastic bags and bottles, aluminum jars, glass containers, waste paper, construction and large -sized garbage from the general stream on the conveyor.
11.

Everything that can be called "raw materials" will be compressed and put into secondary processing
12.

The company is able to process about 300 thousand tons of solid waste per year
13.

According to the factory’s employees, in the Vladivostok garbage, sometimes there are objects that should not be in it - mercury lamps and batteries, which should be disposed of in a special way.
14.

Work on the lines is carried out in 4 shifts of 36 people in shift
15.

Garbage is sorted by categories: paper, glass, aluminum and iron jars, plastic, polyethylene 2 species.
16.

The remaining waste is sent to the general press, where briquettes are formed, 1 cubic meter in size.
17.

In the complex, modern South Korean equipment was installed
18.

19.

This press is used to briquetting aluminum and iron cans
20.

Metal briquettes are immediately sent for processing
21.

Compressed garbage is taken to a special training ground. According to the employees of the complex, the territory for the burial of solid waste was equipped in accordance with all environmental requirements: the infiltration of harmful substances in the soil prevents a special coating, and all garbage drains are sent to special treatment facilities.
22.

23.

The pressed recyclable is taken out for processing. In the morning, several dozen tons of paper and cardboard were taken from here.
24.

Burial landfill
25.

Briquettes are laid in an even layer, which after filling is sprinkled with soil mixed with small garbage (up to 7 cm in diameter). According to the calculations of designers, the landfill with the complex is enough for the next 30 years.
26.

Panorama on the training ground
27.

28.

Powdered hordes are looking for how to profit
29.

30.

31.

32.

33. Wash treatment facilities of the complex

During the operation of the complex in the experimental mode, difficulties arose: Vladivostok garbage was very wet with a lot of organics, it stuck together and scored Vibrosito. As a result, the diameter of the cell had to be increased.
34.

Currently, there are no problems in the equipment, the power of the complex for processing solid waste has reached 300 thousand tons per year. According to experts, this is enough for Vladivostok, especially since the garbage engineering special plant-1, which I will talk about tomorrow, performs similar functions.
35.

The complex for the sorting and processing of solid waste is located at: Kholmysty, 1.
To receive information on the acceptance of municipal solid waste from the population and organizations on the Municipal Unitary Enterprise "Special Plant No. 1", consumers can contact the 8-984-157-3562 call to the senior dispatcher of the MUPV "Specializer No. 1" Suntsova Ekaterina Aleksandrovna.
36.