The Turkish dry load collided with the supports of the working bridge under construction in the Kerch Strait. However, the progress of the construction of the bridge to Crimea was not affected. This was reported to TASS by a source in the Crimean bridge infocrix.
The incident occurred on March 19, but it became known only now. "On March 19, at 23:25 Moscow time, the Lira ship under the flag of Panama, belonging to the company Turkuaz Shipping Corp,, when following the Kerch -Senikalsky channel, deviated from the recommended path in the Buevo 21 and 23A area, and then made it on the structural elements of the working bridge," the source said.
As a result of a collision with a sea vessel, support number 80 was destroyed, including piles with a diameter of 1020 mm and a length of 58 meters, crossbars and heads. Separately clogged lighthouse piles suffered, two more neighboring supports were damaged.
The Crimean Bridge info -center assured that "replacement of supports would not affect the deadlines for the commissioning of the technological bridge." "As a result of the pill of the Lira vessel on the supports of the temporary working bridge N2, which is built between the island of Tuzla and the fairway, the piles of the supports were bent, " RIA "Novosti" quotes the message. "This will not affect the deadlines for the construction of the temporary working bridge. And even more so for the construction time."
The crew of the vessel consisting of nine people was not injured, the dry cargo is put on a raid in the port of Taganrog.
According to Flashcrimea , the damaged bridge is an auxiliary structure for the delivery of goods during the construction of the main structure - a bridge crossing through the Kerch Strait. The Lyra dry cargo is owned by Turkuaz SHIHHHING CORP, it was ruled by a Turkish citizen.
The amount of damage caused is now estimated, reports "Crimea. Realities" with reference to the information center of the Krymsky Bridge project.
The state contract for the design and construction of the bridge across the Kerch Strait was signed on February 17, 2015 between the Federal State Institution "Management of the Federal Roads" Taman Rosavtodor and LLC Stroygazmontazh.
It is planned that in December 2018 construction work will be completed and traffic along the bridge in working mode will be opened. In 2019, after the completion of all commissioning and landscaping of the territory, the bridge is planned to be commissioned.
The Kerch bridge is being built at the expense of the federal budget within the framework of the FCP "Socio-economic development of the Republic of Crimea and the city of Sevastopol until 2020", without the involvement of extrabudgetary financing. The estimated cost of the project is 211.9 billion rubles at the prices of the fourth quarter of 2015.
On March 18, Russian President Vladimir Putin examined the course of building a bridge across the Kerch Strait on the island of Tuzla. During the visit, he demanded to appoint a curator of the project for the construction of a highway from Kerch to Simferopol so that in case of a breakdown of the deadlines it could be "hanged" .