Criminal case
Excited under Part 3 of Art. 286 of the Criminal Code
(exceeding official powers with the causes of grave consequences). Form was detained on June 9, a source in law enforcement agencies told Taiga.info. The issue of choosing a preventive measure is being decided.
Official confirmation in the IC of the Russian Federation for the Novosibirsk region at the time of publication could not be obtained.
I.O. The head of the district administration was appointed managers of the head Oleg Karavaev.
On theft of about 25 million rubles allocated for
pump-filter
The station in Kuibyshev, according to Taiga.info, has already been opened on Part 1 of Art. 286 of the Criminal Code (abuse of authority). The deputy head of the district Valery Konev, who is in the status of the head of the construction department and
Housing and communal services
He oversaw the reconstruction project.
Konev agreed on acts of receiving work performed for an amount exceeding the estimated cost by almost 20 million rubles. The head of the district, Viktor Form,, in turn, did not control his subordinates and did not check the validity of the presentation of the high price for equipment, said a source close to the investigation.
The function was questioned, but refused to testify regarding the misuse of funds, referring to Art. 51 of the Constitution of the Russian Federation. The investigation made an idea to the governor Vladimir Gorodetsky with a request to “resolve the issue of responsibility of the head of the district” for the violations committed (a copy is in the editorial office). The head of the region, in turn, told the taiga.info that the UK had no complaints about Func.
Recall
Control and account
The chamber of the region has found serious violations during the reconstruction
Pumple-filter
Stations. 231 million rubles from the regional and 6.2 million rubles from the city budgets were spent on the facility, but since 2007, not one of the stations was commissioned, and the terms indicated in
Design and estimate
Documentation, were exceeded 3.2 times, the auditors were installed.
The reconstruction investor was the administration of the Kuibyshevsky district,
customer-builder
-
OJSC "Gaztransky"
, established by the government, and the general contractor -
CJSC "Regionontazhstroy"
. The project was developed by specialists of the Novosibirsk State
architectural and construction
University. Such a scheme for conducting and paying for work was created when the Minister of Construction and
Housing and communal services
There was Vladimir Anisimov, and the governor was Victor Tolokonsky.
In 2016, the Novosibirsk Ministry of Construction announced a new competition for the reconstruction of the station. The initial cost of the contract is 125 million rubles. Funds will be allocated from the regional budget.