Contracts for 220 million rubles containing corruption risks found the Accounts Chamber of the Russian Federation when checking the tourist cluster Act "Tunkinskaya Valley" in Buryatia. The deadline for putting the facility into operation was delayed for a year and a half.
The auditors found that the former head of the administration of the Tunkinsky district concluded municipal contracts for the construction of a tourist cluster, as a co -founder of the contractor. Materials on this fact are prepared for transfer to the Prosecutor General.
In the first half of 2017, the readiness of the Tunkinsky Valley amounted to 47%, of which the readiness of the tourist infrastructure - 54.7%. At the same time, the deadline for commissioning was scheduled in 2015. Investment agreements for the 21 objects of tourism infrastructure in the amount of 3 billion rubles have not yet been concluded, which is 80.4% of the total extra -budgetary funds.