The regional GKU "Bridge" announced a competition of dismantling of buildings on both banks of the Ob. About 700 residential and industrial facilities, including capital garages and gas stations, should be demolished until November 20, 2019.
The competition was reported by LLC " Contractor ", LLC "STG Group" and LLC "Destrov". The initial price of the contract amounted to 47.45 million rubles, but Decy reduced it by 35.5% and received it in a row. Money will be allocated from the regional budget.
The company must destroy 77 residential buildings. In some areas, in addition to housing, there are garages, baths and greenhouses. Among the commercial facilities, it is planned to demolish the production buildings of the company Novosibirskskelektroymontazh and Sila-Invest on Stan Danovoe Street, which continue to sue with the authorities, disputing the cost of buildings.
Dece LLC belongs to Anton Tertyshnikov. The company received contracts from the Siberian Branch of the Russian Academy of Sciences, the Office for Housing Issues of the Novosibirsk City Hall, the regional Federal Property Management Agency and the Kurgan Border Institute of the FSB. The Destroy website also says that the company dismantled facing concrete panels from the Tourist Hotel on Marx Square in Novosibirsk.
The Novosibirsk government signed an agreement to build a bridge with the Siberian concession company in December 2017. The SCC belongs to the subsidiary of Gazprombank and the St. Petersburg group "VIS", associated with the ex-head of the Purovsky district of the Yamalo-Nenets Autonomous Okrug Yevgeny Skryabin, businessmen Igor Snegurov and Dmitry Ryabov. The latter works as the general director of TEK Mosenergo JSC Igor Rotenberg, however, representatives of this businessman stated the lack of interests in Novosibirsk. The construction contractor was to become the Avtoban JSC deputy of the Duma of the Khanty-Mansi Autonomous Okrug, United Russia Alexei Andreev, but in May 2019, VIS announced the change of general contractor, clarifying that they would become a subsidiary of the group itself-PF VIS LLC.
The Control and Audit Chamber of the Novosibirsk Region found numerous violations in the conduct of work and the formation of estimates at the initial stage of the construction of the bridge. In the fall of 2018, construction was carried out without permission, in addition, German pipes were purchased with less expensive domestic analogues. The KSP found out that the estimates of preparatory work in 17 positions were overstated 2-3.5 times. The transport committee of the Legislative Assembly recommended that the government revise the concession agreement on the construction of the fourth bridge.