“I have no problem!”, Or drawn bricks


The residents of the house turned for help at the address: Oktyabrsky Ave., 68. Here, a major overhaul of the construction part is undergoing a roof, facade, base, basement. Residents have a question about the installation of supporting beams for balcony plates. As part of the work of the Central Department Store (the Center for Public Control at the Public Chamber of the Kirov Region), a check of the quality of major repairs was checked with the invitation of representatives of the contractor and the organization of Stroynadzor.

At one time, like most schoolchildren, he was read out by the Alexander Volkov’s books cycle about the wizard of the Emerald City, Ellie, Urfin Jus and ... a yellow road. I involuntarily remembered today, seeing a yellow wall of painted brick. Apparently, there was a destruction of brickwork, a plaster layer was imposed on top of the destruction and the characteristic lines of the intercurpical seam were drawn with a finger.

But if this element causes a smile, then the fact that the contractor does not invite the organization of Stroynadzor to carry out hidden work is already a serious violation. First of all, in terms of the installation of balcony beams: installation depth, the presence of a “heel” and sufficient dimension, the requirements for the quality of the cement mixture - all this affects not only the safety of the inhabitants of the apartment, but also passers -by under the balcony. The quality of the device of the blind area can hardly pose any threats to life and health, but this is a fairly expensive element of the common property of the house, and the lack of reinforcement, for example, insufficient height or, again, a violation of the composition of the cement mixture - may subsequently lead to premature costs for restoration work by residents.

There are complaints to destroyed borders, staircase march and asphalt, to install the entrance access doors and their adjacency, the “cleanliness” of the basement and the general clutter of the house territory, the lack of a storm water column at the second entrance, finally. And this is not an exhaustive list.

He asked the Council of the house to the environment to draw up a list of problems, draw up an inspection act and contact the overhaul fund with a request to control the elimination of the identified deficiencies. It is also necessary to insist on the dismantling of balcony beams and work in the presence of representatives of Stroynadzor and the Council of the house. It is also bad that, according to the inhabitants of the house, the Criminal Code of the Criminal Code of self -control of the work of overhaul.

It is significant that the representative of the contractor arrived half an hour later. Immediately to him with the question - you have so many problems ... - I have no problem! Only tasks. By their own admission, the work should have been completed by September 1, and now they are not even taken to indicate the final terms. In the know about the need to invite the hidden works of Stroynadzor. In our presence, he promised to restore the destroyed and clean up - the tenants complained that in communication with them on this issue they received a fundamental refusal.

According to the results of the on -site commission on the quality of the work, a check is planned - I have already sent an appeal to the SRO.

Original