Russian Education Minister Sergei Kravtsov and Governor Transbaikalia Alexander Osipov, on video, took into operation an unfinished school in the village of Kashtak. The concession on its construction was adopted in violation of antimonopoly legislation, noted the publication "Chita.ru". Journalists were not invited to the opening of the school.
On December 23, it was noted in the release of the government that the cost of construction is 1.5 billion rubles, of which 1 billion rubles are budget money, and 500 million rubles are the funds of the investor. The amount will be returned to him for 13 years. The school is designed for 800 students.
"We are grateful to the concessionaire - the company" School of the Future "of the Eastern Arctic Oil and Gas Corporation, Gazprombank, the general contractor of LLC Geolanekhnology for doing everything on time," the minister said on the video.
At the same time, the press service said that "ahead of the commissioning, arrangement of furniture and equipment, and a set of students." The Ministry of Education of the region specified that the entry to school will begin only in April 2023. That is, the first students will appear in it in September next year, but the authorities emphasize that the school was built in just 8 months.

“There is no beautiful innovative school, which is so proud of, there is a box instead of it, not ready either outside or inside, work is underway at the facility, while not to say that it is frantically completed,” writes Chita.ru.
The publication published photos and videos, which shows that finishing work at the school is not completed.