RAO "UES" is preparing for winter
The Board of Directors of the RAO "UES of Russia" heard and took into account information on the preparation of the holding enterprises for the passage of the autumn-winter period of 2006-2007. As part of the repair campaign, by August 1, 2006, turbines were repaired by thermal power plants with a total capacity of 15 216 MW, a total steam production of 71,361 tons/h, hot water boilers with a total capacity of 4,025 Gcal/h, and an overflow of 187.9 km of heating networks was completed.