The commissioning of the school in Zapskovye was postponed immediately to the end of 2028, its construction was suspended a year ago. The head of the economic department of the Pskov region, Andrei Mikheev, admitted the failure of construction: it has not been carried out since June 2025, and the concessionaire ( a subsidiary of VEB ) filed a lawsuit against the Pskov region. A new “road map” has been sent to the federal government for approval, with the deadline for completing the school construction being postponed to the end of 2028, Mikheev said.
The school at the intersection of Engineering and Yunost was supposed to be completed in December 2024; its cost reached almost 3 billion rubles, but this money was not enough.